• August 28, 2018

Abstract on Long-Term Mining Schedule Optimisation accepted for Complex Orebodies Conference 2018

Published on August 28th, 2018

CSA Global is pleased to advise Principal Consultant (Corporate and Business Development) Alexey Tsoy has received confirmation on his abstract: “Long-term mining schedule optimisation” has been accepted for the upcoming Complex Orebodies Conference scheduled between 19-21 November 2018.

The greatest future challenge for the mining industry is that world demand for raw materials is projected to continue to grow for the foreseeable future. Future supply of raw materials will come from a combination of new mine discoveries and recycling. There is mounting evidence that recycling alone cannot hope to replace the future expected demand for metals. To meet future demand much of the supply must be met by the mining of increasingly difficult deposits.

“Complex Ore Bodies” are those deposits that are challenged by the interactions between technical, environmental; community and state, marketing and economic circumstances. In the case of as yet unmined deposits these factors interact so that mining these ore bodies emerge as very complex proposals that are hard to finance. Hence they remain un-mined. As policy evolves to keep up to increasing societal demands new rules create complexity for existing mines, threatening their survival if they cannot adjust to the new environment.

As researchers, policy makers, mining companies, governments and communities rise to these challenges it is becoming increasingly clear that “Complex Orebodies” are the deposits that without solutions to these dynamic and interconnected issues may never be mined. “Current Complex Ore Bodies” are existing mining operations for which the goal posts are changing. In some cases, they are becoming uneconomic due to depth or grade. In others, the environmental impact or societal disruption is such that their continued extraction is untenable. Unless solutions are found, these mines face closure.

ABSTRACT

This abstract describes long term mining schedule optimization approach that may be suitable for complex marginal projects and is based on modern scheduling techniques.

The techniques are an attempt to solve limitations of the Lerch Grossman algorithm that became an industry standard. The algorithm (designed in 1964-1965) is used to define economic viability of a pit by outlining the ultimate pit using economic and mining parameters.

Then mine scheduling is done based on nested shells approach where the same LG algorithm is used to define nested pits with different revenue factors. Somewhere in the process a cut off grade (or series of cut off grades) is calculated to define what material should go to the plant.

A deficiency of Lerch Grossman and fixed cut-off grade(s) is the lack of the concept of time hence no concept of constraints related to the time while mining, as any industrial process, is always constrained by a bottle neck.

It gets even more complicated when a mining project has several alternative processes for the same ore. For example when it has fresh and oxide Cu in the same block (Katanga mineralization style). The solution for pit optimization often requires a customised routine in the optimization software.

A flexible cut-off grade taking into account opportunity costs (Lane, 1988; Rendu 2014) could partially solve the problem and would allow to subordinate other parts of mining enterprise to the constraint/bottle neck. But it means introducing complexity into scheduling process. And introduction of several processing streams increases number of required cut-off calculations dramatically.

The proposed approach is based on using economic value of each block and apply constraints to physical throughput units in the system. Thus it allows to avoid using the proxy of economic value such as cut-off grade. The model is then run through an integer linear programming algorithm to optimize the schedule trying to achieve maximum NPV. The approach was initially described by Thys Jonson in 1968.

The constraints can be defined in different units and applied in parallel. For example, a total mining capacity in tons, plus total crushing capacity in BWi (energy), oxide ore capacity (in tonnes), total deleterious elements content (in tonnes) in a period and other parameters can be defined simultaneously. The ultimate goal is to get a schedule with maximum NPV.

Limitations of the approach are the consequences of its advantages – the resulting schedule is strategic in nature and will require further analysis and design work, and sometimes what is the most economic solution in long term is not always what a company may require right now. An example of the latter may be a cash strapped miner that would prefer to sacrifice long term NPV to this year’s cashflow.

alexey_tsoy_suit_thumbnail-237x355

Alexey Tsoy
Diploma – International Economics, OERN (Subsoil Use Expert Society of Russia)
Principal Consultant (Corporate & Business Development)

Alexey is a Principal Consultant of Corporate and Business Development and possesses more than 15 years’ commercial experience in contract negotiations, sales, marketing and business development. He led several complex resource and reserve estimation projects as Project Manager. He is also a contributor to major Russian mining and geology magazines on international reporting standards for reporting on resources and reserves, on the impact mining has on the general economy and the required changes to maximize it.

Complex Orebodies Conference 2018

How can we help?

Contact us to discuss how we can help your organisation.

SIGN UP FOR EMAIL ALERTS

CONNECT WITH CSA GLOBAL